Most renovation budgets are not blown by expensive materials. They are blown by doing the right job at the wrong time: a new floor laid before the plasterers arrive, a bathroom tiled before anyone checks the pipework behind it, a freshly painted hallway used as a route for carrying out rubble.
The order of works exists to stop that. It is the same on a full house refurbishment as it is on a single room, and it runs roughly like this.
1. Survey the house before you plan the rooms
Before anyone decides on kitchen units, find out what the house is actually dealing with. Damp, failed pointing, a sagging roof, old wiring, bowing plaster, movement around the bay. These things decide the budget far more than the choice of worktop, and they are much cheaper to deal with before the finishes go in.
If structural work is involved — removing a wall, forming an opening, converting a loft — it needs designing and signing off at this stage, not halfway through. Building Regulations approval and, where applicable, planning permission belong at the start of the job.
2. Make it sound and weathertight
Roofing, gutters, pointing, render, windows and doors come next. There is no sense in plastering a wall that is still getting wet from the outside, and no sense in decorating under a roof that is due to be stripped.
This is also when a lot of homeowners find their first unwelcome surprise. It is better to find it now, with bare walls, than after the second fix.
3. Strip out
Old kitchens, bathrooms, floor coverings, defunct pipework, dead cables. Strip-out is noisy, dusty and the point at which the house looks worse than when you bought it. It is also when hidden problems become visible, so allow a little contingency immediately after it.
- Protect anything you are keeping — original doors, fireplaces, cornices, stair spindles — before the first bag of rubble is moved.
- Decide early what is being salvaged. Once something is out and stacked in a skip, that decision is made for you.
4. First fix
First fix is everything that disappears into the walls and floors: wiring, pipework, drainage, stud walls, insulation, door linings, and anything that needs to be in place before the plaster goes on. It is slow, invisible work, and it is where rushing causes the most expensive mistakes.
Take photographs of every wall before it is closed up. In two years, when someone wants to hang a shelf or fit a towel rail, those photographs are worth more than any guarantee.
5. Plaster
Plastering is the dividing line of the whole project. Everything messy happens before it; everything delicate happens after. Plaster also needs time to dry out properly — the timing depends on the thickness, the room and the ventilation, so take your plasterer’s advice rather than a figure from the internet.
Painting over plaster that has not dried out is one of the most common reasons decorating fails within a year.
6. Second fix
Now the house starts looking like a house. Sockets and switches, radiators, sanitaryware, kitchen units, internal doors, skirting, architraves, handrails. The kitchen and bathroom usually go in at this stage, after plastering and before final decorating.
One point that catches people out: if you are fitting a new floor later, the finished floor height affects door clearances, thresholds and whether an internal door can swing over a mat. Agree the floor build-up before the doors are hung.
7. Decorate
Caulking, filling, sanding, mist coat, then the proper coats. Decorating is the stage everyone wants to rush, and the one that makes or breaks the perceived quality of the whole job. The preparation takes longer than the painting, and it is what separates a finish that lasts from one that shows every flaw by the following winter.
8. Floors — and why it depends
Flooring is the one stage that genuinely moves around, and the honest answer to “floors or paint first?” is that it depends on the floor:
- Solid or engineered wood that will be sanded and finished on site: fit it before the final coats of paint, because sanding throws dust everywhere.
- Carpet, laminate and LVT: fit after decorating, so the floor is not being walked over, taped and splashed.
- Tiles in a bathroom or kitchen: tile before the final coats, then cut in afterwards.
If you want the full sequence set out stage by stage, with the stage-by-stage detail and the common questions answered, there is a step-by-step guide to the order of works that covers it in more depth.
9. Sign-offs and snagging
Collect the paperwork while the trades are still on site, not six months later when you are selling: electrical certificates, gas safety records, Building Control completion, warranties for windows, boilers and roofing. Then walk every room in daylight and write a snagging list in one go, rather than sending a trickle of messages over several weeks.
Living in the house while the work happens
Most people cannot move out, and the order of works has to bend around that. The usual approach is to keep one room sealed off and liveable, keep the existing kitchen or bathroom running for as long as the sequence allows, and accept that the dusty stages — strip-out and plastering — are the ones worth escaping for a few days if you can.
Agree with your builder, in advance, which room comes back into use first. It makes a long project far easier to live with.
The short version
Work from the outside in and from the structure to the surface. Deal with what is holding the house up and keeping the weather out, then the services, then the plaster, then the fittings, then the finishes. Every stage that gets taken out of turn is paid for twice — once when it is installed, and again when it is protected, repaired or replaced.
About the author
This article was written by the team at Eli Refurbishments, a refurbishment company based in Romford carrying out house and flat refurbishments, kitchens, bathrooms, joinery, flooring and decorating across London and Essex.

A boiler that stops working at 10pm on a cold weekend feels urgent very quickly, especially when there is no heating, no hot water, or a fault code flashing on the display. The first instinct is usually to press reset a few times and hope it comes back. Sometimes that works, but often it does not, and repeatedly resetting can hide a problem that needs looking at properly.